By Categories: Economy, Editorials

Note:-Use this article wisely in your answers. It can help you in emphasizing the importance of infrastructural mega projects and what they mean for an economy. For instance – Dubai’s international airport is the world’s busiest, accounting for 21 percent of Dubai’s employment and 27 percent of its GDP (A Single mega project of such caliber, until you look at the the numbers it seems unbelievable and is evident of the fact that infrastructure is the key to economic growth). You can use similar statistics and details mentioned in the article below in your answer when you write about infrastructure.

The below editorial can also give you ample analysis to pin point  the faults in PPP  projects and why they fail and the few which succeed – why they succeed ?

Lets take a question an try answering it.

Question – “It is said that India has voracious appetite for infrastructure, and there is a need for the overhauling the infrastructure altogether and diversify them”. In light of this analyse the importance of infrastructure, its trans-formative impact on economy in general and on lives of people in particular. Substantiate your answer with valid arguments.

(The statement was given by FM Arun Jaitley in one of his interviews)

Answer– :- If you open your answer like – “Infrastructure is the greatest enabler not only of economy but also of live of people” and then go on giving few more generalized statements in your answer it might not be bad but it might not fetch you the extra 2-3 marks. But if you open the statement with an example of Dubai airport or Panama canal (read the article below) then it gives an impression to the examiner that you are well-read and you have evidence to prove it. Statistics, when used wisely can take your answer to next-level and makes your answer more interesting and mark-fetching.



Infrastructure megaprojects are crucial to the future of cities, states, and individual livelihoods. The problem is that these projects often go off the rails, either with regard to budget or time—or both.

However, it’s important to remember that building and maintaining infrastructure is a critical and sometimes even lifesaving undertaking. Sewage and water-supply systems, for example, keep diseases such as cholera at bay. Much of the Netherlands would be under water without the North Sea Protection Works, which guards that low-lying country’s landscape.

Big infrastructure projects can also be economically transformative. Consider the Panama Canal. It accounts for a significant share of the country’s GDP. Dubai’s international airport is the world’s busiest, accounting for 21 percent of Dubai’s employment and 27 percent of its GDP. And Hong Kong would surely grind to a halt without its clean and speedy subway system, the MTR, which has enabled the densely packed city to build beyond the downtown districts.

All these megaprojects have worked as intended; indeed, it is almost impossible to think of these places without them. Not surprisingly, all of them are being expanded. Also not surprisingly, the canal and airport projects are both running late and well above the initial budget; even the hyperefficient MTR has run into delays with some of its projects.

The world needs to spend about $57 trillion on infrastructure by 2030 to enable the anticipated levels of GDP growth globally. Of that, about two-thirds will be required in developing markets, where there are rising middle classes, population growth, urbanization, and increased economic growth. These countries need infrastructure, but all too often many years will pass and the promised road, bridge, and metro projects still will not have materialized.

The risks associated with megaprojects—those that cost $1 billion or more—are well documented. In one influential study, Bent Flyvbjerg( “What you should know about megaprojects and why: An overview,” Project Management Journal, 2014), an expert in project management at Oxford’s business school, estimated that nine out of ten go over budget.

Rail projects, for example, go over budget by an average of 44.7 percent, and their demand is overestimated by 51.4 percent. Bridges and tunnels incur an average 35 percent cost overrun; for roads, it’s 20 percent. Given that many projects are approved with a 20 percent return on investment expected, this leaves governments to pick up the tab for the rest.

Time overruns, too, are a perennial problem. Consider the metro system in Salvador, Brazil. Construction began in 2000, but it took more than a dozen years for the first passengers to ride it; most of the work is still unfinished. It has taken New York a decade just to begin the $3.9 billion project to rebuild the 59-year-old Tappan Zee Bridge; meanwhile, the cost of maintaining the worn-out bridge keeps increasing.

Finally, the premise that projects need to work on two levels—in the short term for recovering financial outlays and the longer term for creating social impact—often becomes a barrier to taking action. Even projects that are needed do not get executed, especially in places where revenues from a project are unlikely to cover its cost.

How can companies and governments do better to build megaprojects that deliver their societal benefits and do so on time and on budget?

Why projects go bad

There are three main reasons for failure.

Overoptimism and overcomplexity. In order to justify a project, sometimes costs and timelines are systematically underestimated and benefits systematically overestimated. Flyvbjerg argues that project managers competing for funding massage the data until they come under the limit of what is deemed affordable; stating the real cost, he writes, would make a project unpalatable. From the outset, such projects are on a fast track to failure.

A common example of this comes when big projects cross state or national borders and involve a mix of private and government spending. For example, a new railway could involve three national governments, numerous local governments, different environmental and health standards, varied degrees of skills and wage expectations, and dozens of private contractors, suppliers, and end users. Just one issue can stall the process indefinitely. In one case, for example, it took two countries a decade to work out the diplomatic considerations that allowed them to build a hydroelectric dam. All too often, these complicating issues are not deeply considered or priced to the fullest before launching a project.

One useful reality check is to compare the project under consideration to similar projects that have already been completed. Known as “reference-class forecasting,” this process addresses confirmation bias by forcing decision makers to consider cases that don’t necessarily justify the preferred course of action. For example, if a city wants to build a ten-kilometer metro line with four stations, it should look at other cities that have built similar lines to understand the true cost and time dynamics.

Poor execution. Having delivered an unrealistically low project budget, the temptation is to cut corners to maintain cost assumptions and protect the (typically slim) profit margins for the engineering and construction firms that have been contracted to deliver the project. Project execution, from design and planning through construction, is riddled with problems such as incomplete design, lack of clear scope, ill-advised shortcuts, and even mathematical errors in scheduling and risk assessment.
A McKinsey study of 48 troubled megaprojects showed that poor execution was responsible for cost and time overruns in 73 percent of the cases; for the rest, these were due to politics, such as new governments or laws.
In part, execution is poor because many projects are so complex that what might seem like routine issues can become major headaches. For example, if steel does not arrive at the job site on time, the delay can stall the entire project. Ditto if one of the specialty trades has a problem. Higher productivity will not compensate for these shortfalls because such delays tend to ripple through the entire project system.

Another challenge is low productivity. While the manufacturing sector has approximately doubled its productivity over the past two decades, construction productivity has remained flat or even declined. Wages, however, have continued to rise faster than inflation in many markets, resulting in higher costs for the same results.

A recent McKinsey study have shown that delivering infrastructure more efficiently can reduce its whole cost by 15 percent. Up-front preparation pays for itself many times over. All told, efficiency gains in approval, engineering, procurement, and construction can generate savings of as much as 25 percent on new projects, without compromising the quality of outcomes.

Weakness in organizational design and capabilities. Many entities involved in building megaprojects have an organizational setup in which the project director sits four or five levels down from the top leadership. The following structure is common:

  • Layer 1: Subcontractor to contractor
  • Layer 2: Contractors to construction manager or managing contractor
  • Layer 3: Construction manager to owner’s representative
  • Layer 4: Owner’s representative to project sponsor
  • Layer 5: Project sponsor to business executive

This is a problem because each layer will have a view on how time and costs can be compressed. For example, the first three layers are looking for more work and more money, while the later ones are looking to deliver on time and budget. Also, the authority to make final decisions is often remote from the action.

Capabilities, or lack thereof, are another issue. Large projects are typically either sponsored by the government or by an entrepreneur with bold aspirations; they can take 10 to 15 years to finish. Even individuals who build large infrastructure projects for a living may execute only three or four megaprojects in a lifetime. Because each one is unique, the learning curve is steep every time, and the skills needed are scarce. All these problems are compounded by the speed at which projects get started. Starting from scratch, megaprojects may have to create organizations of several thousand people in 12 to 18 months—a significant operational and managerial challenge equivalent to creating a new start-up company.

How to deliver on the promise of megaprojects

Any big project carries a big opportunity for failure, but regularly going over time and over budget implies that there are systematic errors at work. And that means these problems can be identified and addressed.

The process for selecting projects needs to be fact based and transparent to ensure accountability. South Korea shows one promising approach. In 2005, it established the Public and Private Infrastructure Investment Management Center (PIMAC) to get accurate data on costs and benefits; PIMAC does feasibility studies on public megaprojects, conducts value-for-money tests, sponsors comprehensive research on improving public investment, and evaluates projects when they are done. So far, PIMAC has rejected almost half the projects that it has reviewed. Before PIMAC, the rejection figure was 3 percent.

Distressed projects have another thing in common: they lack adequate controls. Specifically, they do not have robust risk-analysis or risk-management protocols and do not provide timely reporting on progress relative to budgets and timelines. The data used to report on project progress are typically outdated (as they generally rely on payments to contractors rather than on actual work performed) and not aligned with the true progress of the project. In addition, baselines get adjusted time and again, and contractors and owners use different metrics to measure progress. It is problematic when there are multiple estimates of the cost and time performance of the project relative to the baseline, which means there is no common understanding of performance. This limits the partners’ ability to figure out how to accelerate project delivery and control cost overruns.

A more sophisticated approach is to use real-time data that measures activity in the field, such as cubic meters of concrete poured or earth moved, relative to work plans and budgets. This differs from the usual approach, which is to track progress by measuring funds paid to contractors relative to budget. Measuring progress on the basis of cash flow, however, is less than ideal, because usually it takes more than 30 days to pay. That means the related data are out of date; moreover, payments to contractors may not correlate to actual construction progress. Improving project performance requires better planning and preparation in three areas.

Do the engineering and risk analysis before starting construction. This is often stated but rarely followed, though doing so clearly improves project performance. Edward Merrow, the founder of the Independent Project Analysis consultancy and author of a book on megaprojects, Edward W. Merrow, Industrial Megaprojects: Concepts, Strategies, and Practices for Success, has shown that the best examples of project-definition work reduce both project timelines and costs by roughly 20 percent.

Most project-development organizations or project sponsors are reluctant to spend a significant amount of money on early-stage engineering and design for three reasons. First, they often lack the funds in the early stage of a project to spend significantly on design and engineering. Second, they are eager to break ground and start construction. Finally, they worry that the design will be modified once construction is under way and thus make the expenditure on up-front design pointless.

Streamline permitting and land acquisition. It’s not unusual that it takes longer to get approvals for a project than to build it. Best practices in issuing permits involve prioritizing projects, defining clear roles and responsibilities, and establishing time limits all along the way, including on public review. Providing “one stop shop” permitting can help. By applying these approaches, England and Wales cut the time to approve power-industry infrastructure from 12 months to 9, compared with an average of four years in the rest of Europe.

Projects can also be designed to reduce time-consuming land battles. The state of Virginia completed a plan to widen Interstate 495 in 2012, after a private design company came up with a plan that cut costs markedly and eliminated the need to remove hundreds of homes.

Build a project team with the right mix of abilities. Without a well-resourced and qualified network of project managers, advisers, and controllers, projects will not deliver the best possible return on investment. At worst, they will fail.

Investors and owners need to take an active role in putting together the project team. It is not enough for them to have a vague theoretical overview of how the project should work. They need to create a detailed, practical approach to deal with such likely eventualities as managing quality risks, escalating contractor’s costs, or replacing a high-tech supplier. An experienced project manager is not enough; players must assemble a team that has all the requisite skills, including legal and technical expertise, contract management, project reporting, regulatory approval, stakeholder management, and government and community relations.

The world needs megaprojects to deliver the economic and social goods that billions of people lack and to create the economic growth that will pay for them. But a bad project has consequences that go well beyond a specific bridge, tunnel, or sewage system. Getting it right, or at least better, is good for everyone.


 

Share is Caring, Choose Your Platform!

Recent Posts


    In a diverse country like India, where each State is socially, culturally, economically, and politically distinct, measuring Governance becomes increasingly tricky. The Public Affairs Index (PAI 2021) is a scientifically rigorous, data-based framework that measures the quality of governance at the Sub-national level and ranks the States and Union Territories (UTs) of India on a Composite Index (CI).


    States are classified into two categories – Large and Small – using population as the criteria.

    In PAI 2021, PAC defined three significant pillars that embody GovernanceGrowth, Equity, and Sustainability. Each of the three Pillars is circumscribed by five governance praxis Themes.

    The themes include – Voice and Accountability, Government Effectiveness, Rule of Law, Regulatory Quality and Control of Corruption.

    At the bottom of the pyramid, 43 component indicators are mapped to 14 Sustainable Development Goals (SDGs) that are relevant to the States and UTs.

    This forms the foundation of the conceptual framework of PAI 2021. The choice of the 43 indicators that go into the calculation of the CI were dictated by the objective of uncovering the complexity and multidimensional character of development governance

    The Equity Principle

    The Equity Pillar of the PAI 2021 Index analyses the inclusiveness impact at the Sub-national level in the country; inclusiveness in terms of the welfare of a society that depends primarily on establishing that all people feel that they have a say in the governance and are not excluded from the mainstream policy framework.

    This requires all individuals and communities, but particularly the most vulnerable, to have an opportunity to improve or maintain their wellbeing. This chapter of PAI 2021 reflects the performance of States and UTs during the pandemic and questions the governance infrastructure in the country, analysing the effectiveness of schemes and the general livelihood of the people in terms of Equity.

    Growth and its Discontents

    Growth in its multidimensional form encompasses the essence of access to and the availability and optimal utilisation of resources. By resources, PAI 2021 refer to human resources, infrastructure and the budgetary allocations. Capacity building of an economy cannot take place if all the key players of growth do not drive development. The multiplier effects of better health care, improved educational outcomes, increased capital accumulation and lower unemployment levels contribute magnificently in the growth and development of the States.

    The Pursuit Of Sustainability

    The Sustainability Pillar analyses the access to and usage of resources that has an impact on environment, economy and humankind. The Pillar subsumes two themes and uses seven indicators to measure the effectiveness of government efforts with regards to Sustainability.

     

    The Curious Case Of The Delta

    The Delta Analysis presents the results on the State performance on year-on-year improvement. The rankings are measured as the Delta value over the last five to 10 years of data available for 12 Key Development Indicators (KDI). In PAI 2021, 12 indicators across the three Pillars of Equity (five indicators), Growth (five indicators) and Sustainability (two indicators). These KDIs are the outcome indicators crucial to assess Human Development. The Performance in the Delta Analysis is then compared to the Overall PAI 2021 Index.

    Key Findings:-

    1. In the Large States category (overall), Chhattisgarh ranks 1st, followed by Odisha and Telangana, whereas, towards the bottom are Maharashtra at 16th, Assam at 17th and Gujarat at 18th. Gujarat is one State that has seen startling performance ranking 5th in the PAI 2021 Index outperforming traditionally good performing States like Andhra Pradesh and Karnataka, but ranks last in terms of Delta
    2. In the Small States category (overall), Nagaland tops, followed by Mizoram and Tripura. Towards the tail end of the overall Delta ranking is Uttarakhand (9th), Arunachal Pradesh (10th) and Meghalaya (11th). Nagaland despite being a poor performer in the PAI 2021 Index has come out to be the top performer in Delta, similarly, Mizoram’s performance in Delta is also reflected in it’s ranking in the PAI 2021 Index
    3. In terms of Equity, in the Large States category, Chhattisgarh has the best Delta rate on Equity indicators, this is also reflected in the performance of Chhattisgarh in the Equity Pillar where it ranks 4th. Following Chhattisgarh is Odisha ranking 2nd in Delta-Equity ranking, but ranks 17th in the Equity Pillar of PAI 2021. Telangana ranks 3rd in Delta-Equity ranking even though it is not a top performer in this Pillar in the overall PAI 2021 Index. Jharkhand (16th), Uttar Pradesh (17th) and Assam (18th) rank at the bottom with Uttar Pradesh’s performance in line with the PAI 2021 Index
    4. Odisha and Nagaland have shown the best year-on-year improvement under 12 Key Development indicators.

    In the Scheme of Things

    The Scheme Analysis adds an additional dimension to ranking of the States on their governance. It attempts to complement the Governance Model by trying to understand the developmental activities undertaken by State Governments in the form of schemes. It also tries to understand whether better performance of States in schemes reflect in better governance.

    The Centrally Sponsored schemes that were analysed are National Health Mission (NHM), Umbrella Integrated Child Development Services scheme (ICDS), Mahatma Gandh National Rural Employment Guarantee Scheme (MGNREGS), Samagra Shiksha Abhiyan (SmSA) and MidDay Meal Scheme (MDMS).

    National Health Mission (NHM)

    • In the 60:40 division States, the top three performers are Kerala, Goa and Tamil Nadu and, the bottom three performers are Uttar Pradesh, Jharkhand and Bihar.
    • In the 90:10 division States, the top three performers were Himachal Pradesh, Sikkim and Mizoram; and, the bottom three performers are Manipur, Assam and Meghalaya.

     

    INTEGRATED CHILD DEVELOPMENT SERVICES (ICDS)

    • Among the 60:40 division States, Orissa, Chhattisgarh and Madhya Pradesh are the top three performers and Tamil Nadu, Telangana and Delhi appear as the bottom three performers.
    • Among the 90:10 division States, the top three performers are Manipur, Arunachal Pradesh and Nagaland; and, the bottom three performers are Jammu and Kashmir, Uttarakhand and Himachal Pradesh

     

    MID- DAY MEAL SCHEME (MDMS)

    • Among the 60:40 division States, Goa, West Bengal and Delhi appear as the top three performers and Andhra Pradesh, Telangana and Bihar appear as the bottom three performers.
    • Among the 90:10 division States, Mizoram, Himachal Pradesh and Tripura were the top three performers and Jammu & Kashmir, Nagaland and Arunachal Pradesh were the bottom three performers

     

    SAMAGRA SHIKSHA ABHIYAN (SMSA)

    • West Bengal, Bihar and Tamil Nadu were the top three States amongst the 60:40 division States; while Haryana, Punjab and Rajasthan appeared as the bottom three performers
    • In the case of 90:10 division States, Mizoram, Assam and Tripura were the top three performers and Nagaland, Jammu & Kashmir and Uttarakhand featured as the bottom three

     

    MAHATMA GANDHI NATIONAL RURAL EMPLOYMENT GUARANTEE SCHEME (MGNREGS)

    • Among the 60:40 division States, the top three performers are Kerala, Andhra Pradesh and Orissa and the bottom three performers are Madhya Pradesh, Jharkhand and Goa
    • In the 90:10 division States, the top three performers are Mizoram, Sikkim and Nagaland and the bottom three performers are Manipur and Assam